Skip to main content

Picture perfect

It's a little past midnight (basically Wednesday morning) and we're putting finishing touches on our yoyos. This past week has been a whirlwind, but we finally made it through. Check it out!



We just finished assembling all 50 yoyos, string and all. Here's a summary of what we the last few days.

Thursday, 5/9

  • Tested the photo molds with the key — it worked! We found that the photo piece shrunk slightly more than anticipated, so we remachined the photo mold to be a bit wider at the based so that it can't slip into the yoyo body cavity. Also touched up the mold bottoms with a finer stepover to be perfectly smooth. 
  • Put together our first full assembly. So satisfying! Featuring a magnetic click.
Friday, 5/10
  • A few more touch-ups on the photo mold.
  • Sanded molds so that machining features didn't show up on injection molded parts.
  • Tested photo molds
  • Honed injection molding parameters for top piece
  • Filed down thermoform die after realizing the piece did not fit after shrinkage

Saturday, 5/11

  • Filed the die too much... so re 3D printed the thermoform die.
  • First production run of the photo piece! Decided to make it purple.
  • Modified and recut shoulder bolts for body printing
Sunday, 5/12
  • Production run (nearly) of the top camera piece
  • Tested out thermoform die
Monday, 5/13
  • Finished top piece production run
  • Bottom piece production run
  • Thermoform lens production run & cutting
Tuesday, 5/14
  • Body production run
  • ASSEMBLY
  • Powerpoint and this blog.

It's a little crazy to think that we're (nearly) on the flip side of this whole process. At the end of it all, we know we have learned an insane amount! Beyond just looking at things and being able to tell how they were made (which is pretty cool already), we all were talking about how we've internalized the design process and can easily follow and understand the choices that are made. If we did this yo-yo again, there are so many steps we would take differently! We improved our team skills and learned how to communicate and collaborate for technical work. 

Overall, we're really excited and happy with the finished product. We're most excited that it's new! And when we think about how many new things we tried — the registration, the magnetic mechanism, the pegs, the non-circular non-symmetric design — we're really happy to have a piece in our hand that works. 

Huge huge thank you and shout out to Wade, Joe, and Dan for all your help, for being so patient with us, and for keeping the shop open at many unreasonable hours. We appreciate it so much. 

Comments

Popular posts from this blog

Setting up our first (SNAP)SHOTS!

It's crunch time now! This week we made a lot of great progress and now have a more concrete plan for the rest of the semester. Here is our manufacturing schedule for the yolaroid! Yolaroid Manufacturing Schedule for this last week and the upcoming week Our biggest achievement this week is we made our first molds in lab! It took us a while to figure out how to use the mill but doing our first bit of machining together was a great learning experience. It didn't take us too long with the staff to start familiarizing ourselves with the mill and our first molds for the Yolaroid body came out really well! Maybe by the end of the semester we will be just as one with the machine as Joe! First Yolaroid molds! For lab this week, we are ready to begin injection molding the Yolaroid body as a team. Working as a team to walk through machining the molds as well as injection molding will allow us to split up some work for making the other molds and injection molding pie

Getting in focus

This week, we made many changes to our design for manufacturing and design-related reasons. We finished machining 3 of the 4 molds for injection molding, created a plan for the design of our magnetic photo piece, printed on plastic and successfully thermoformed the camera lens, and tested injection molding for two of our pieces (including checking the snap fit on the pegs). Things seem to be in good shape! Check out our progress sheet here .  Machining At this point, machining hurdles are somewhat expected — but it seemed like we ran into many this week! The CAM for the camera front pieces (both top and bottom) proved difficult for two main reasons: (1) For the camera bottom piece, it was nearly impossible to generate a tool path that successfully removed enough material for the snap fit of our very small magnet. After trying horizontals, pencils, and several other finishing paths, we finally found the settings to sufficiently clean up the magnet hole (with a scallop, fol

Capturing Our Desired Design

Over the past couple weeks, we’ve experienced some machining set-backs, but we have successfully machined all of our molds (except the photo mold, which will be machined today in class!). We have created our first assembled yoyo, which can be seen in the picture at the right . One of the issues that we had was that we accidentally machined our holes too large for our dowel pins, so we had to remachine the cores of the top and bottom camera piece with a smaller diameter. We then had to ream our holes and press fit in our dowel pins. We learned that the difference between what should work in paper and what does in real life is significant: our holes needed to fit 5/64” pins, but we ended up only reaming to .076” because the holes were too large the previous time. This time they fit perfectly, which was super satisfying for our team. Previously, we had used Loctite, which had super inconsistent results - one of our dowel pins fell into the mold and the other one broke right off. We al